What need to be paid attention when removing the frame scaffolding

1) Preparation work before removing frame scaffolding: comprehensive review of scaffolding, focusing on checking the fastener connection and support system. According to the inspection results and site conditions to prepare the demolishing scheme and approved by the department to do technical clarification. In addition, set up a fence or warning signs and have special staff to remove the scaffolding residue and other debris on time.
2) Work area of removing frame scaffolding, prohibited non-operator to enter
3) When removing the frame scaffolding, there must have a special person to commend so that echo up and down, action coordination.
4) It is strictly prohibited to push or pull down the frame scaffolding directly.
5) Fixed parts should be removed with the scaffolding layer, when removed the last section of the riser, we should build temporary support to reinforce, then removed fixed parts and support.
6) Removed the scaffolding components should be promptly transported to the ground, it is strictly prohibited to throw from the air.
7) After removed, the scaffolding parts should be promptly cleaned and maintained. According to the need to brush rust paint, and according to varieties, specifications to stacked storage.