Housing construction project: scaffolding lap way and use purpose

图片
Housing construction project: scaffolding lap way and use purpose (1) - used to support the template form scaffolding, scaffold materials, authors of shelf. (2) single scaffold - referred to as "single frame, or only a row of vertical rod, one end of the transverse horizontal bar on a scaffold on the wall. (3) double row scaffolding - referred to as "double bent, by inside and outside the two rows of stud and level of the scaffold pole, etc. (4) to decorate the scaffold - used for decoration engineering construction work. (5) structure of the scaffold - used for building and structure engineering construction work. 6. Cantilever scaffold - applied to equipment installation or maintenance cantilevers. http://www.hunanworld.com/

The advantages and disadvantages of housing construction project: coupler scaffold

图片
The advantages and disadvantages of housing construction project: coupler scaffold 1, the advantages 1) the bearing capacity is bigger. When scaffold geometry and structure meet the requirements of the specification, under normal circumstances, the scaffolding of the bearing capacity of single pipe column can reach 15 kn ~ 35 kn (1.5 ~ 3.5 tf, tf design values). 2) convenient installation and erection of flexible. Due to the length of steel tube is easy to adjust, fastener connection is simple, and can adapt to all kinds of plane, elevation of buildings and structures in the scaffold. 3) to compare the economy. Simple processing, an investment cost is low. If carefully designed scaffold geometry size, pay attention to improve the steel pipe flow utilization rate, the dosage of material also can obtain good economic effect. Fastener steel pipe frame or steel used quantity of about 15 kg per square metre. 2 and disadvantages 1) fasteners (especially its screw) easy to lose. 2) nod

Housing construction project: scaffolding safety related requirements

图片
Housing construction project: scaffolding safety related requirements 1, the build-up of high-level scaffolding, adopted by the various materials must meet the quality requirements. 2, high-level scaffolding foundation must be strong, before the erection of the computation, meet the requirement of load, and set-up, and according to the construction of drainage measures. 3, scaffolding, technical requirements should comply with the regulations of relevant specification. 4, must attach great importance to all kinds of structural measures: bridging, node, etc. Shall be set up according to the requirement. 5, horizontal closed: should be the first step, every step or two step, be put with scaffolding plank hand or foot basketry, scaffolding to laid along, overlapping joint should be shelved in a small bar, it is forbidden to appear short board. And in every four step laid between stud and metope system bottom has long security. Step 6, vertical closed: from the second to fifth step,

Housing construction project: the characteristic and the scaffold

Housing construction project: the characteristic and the scaffold And scaffolding and called every scaffold, is a kind of scaffolding scaffolding construction process. Density and relative to other scaffolding scaffolding system, namely which full house. The scaffold and the scaffold relative to other more solid. The characteristics of And the scaffold is mainly used for single factory building, exhibition hall, gymnasium, etc. The height, width and large building at the top of the decoration construction. By the vertical rod, bar, rod, scissors, etc. After use and scaffolding, 3.6 meters above the interior wall decoration not calculated the scaffold, and the interior wall masonry scaffolding as stipulated in the scaffold in the calculation. And scaffolding used depends on the height of the casing under the clear height of 3.6 M, no matter which kind of decoration, ceiling adopts are calculated not decorate the scaffold. The shed clear height between 3.6 M and 5.2 M, the adornmen

Housing construction project: the scaffold construction technical measures of the rainy season

图片
Housing construction project: the scaffold construction technical measures of the rainy season Scaffolding is the important place to workers in the construction operation, its security and stability directly affect the workers' life safety and the safety of buildings. In case of the rain period construction, scaffold should take the following measures: 1) scaffold shall set up hard, thick concrete foundation should be 100 or more. 2) add appropriate and the structure of the connecting rods, which can enhance the stability of the scaffold and the ability to resist overturning, and connecting rods in all parts of the check in time. 3) scaffold on the footpath place for people to access should do well such as slip and fall prevention measures. 4) rainy day should not be conducted on scaffolding construction, such as must be on the scaffolding operation, to control the scaffolding on the number of personnel, artifacts and other building materials. 5) metal scaffolding to leakage

Housing construction project: scaffolding safety net set method

图片
Housing construction project: scaffolding safety net set method Safety net is one of the important facilities of the construction safety protection, safety net should be set in the construction organization design has clear rules and requirements, technologically sophisticated design should be done. Safety net type: safety net by hanging vertical and horizontal set way points two kinds. Vertical set 1. Vertical set used in high-rise building construction scaffolding, more lat eral hung safety net enclosure, generally USES fine woven nylon rope safety net. Scaffolding safety net should be sealed, and external fixation. 2. The level of safety net Level of safety net for multilayer construction scaffolding, more is to use hemp rope 9 mm in diameter, coir rope or nylon rope weaving, general specifications for the 3 m by 6 m, 5 cm of mesh, each a good safety net should be able to withstand the pounding of not less than 1600 n load. Up from the floor on the second floor of its a safety net,

Housing construction project: the scaffolding steel pipe design requirements

图片
Housing construction project: the scaffolding steel pipe design requirements Role in the load of scaffold can be divided into permanent load (constant load and variable load (load). Meter bearing component of scaffolding, should according to the use that may occur during the process of load calculated, take its the most unfavorable combination general should carry on the design and calculation of the following: (1) the longitudinal and transverse horizontal pole flexural member's strength and the connection anti-sliding bearing capacity calculation of fasteners. (2) the stability of the vertical rod is calculated. (3) even the wall is a strength, stability, and the connection strength calculation. (4) post foundation bearing capacity calculation. http://www.hunanworld.com/

Housing construction project: cuplock scaffolding

图片
Housing construction project: cuplock scaffolding Cuplock of fastener type steel pipe scaffold scope and fastener type steel pipe scaffold basic same, mainly for the following project: 1) according to the specific construction requirements, combined into different group size and carrying capacity of exterior wall construction with single and double row scaffolding. 2) are widely used in the overpass Bridges, culverts, tunnels, construction and other engineering construction, the concrete structure construction formwork support frame and shores. 3) adhesive lifting scaffolding frame body, a variety of functions such as cantilever scaffold construction equipment erection of space structure. 4) ShiDing tent, tent, lighthouse structures, authors, etc. 5) chimney, water tower scaffold building curve type, such as body, authors. http://www.hunanworld.com/

Housing construction project: scaffolding lap way and use purpose

图片
Housing construction project: scaffolding lap way and use purpose (1) - used to support the template form scaffolding, scaffold materials, authors of shelf. (2) single scaffold - referred to as "single frame, or only a row of vertical rod, one end of the transverse horizontal bar on a scaffold on the wall. (3) double row scaffolding - referred to as "double bent, by inside and outside the two rows of stud and level of the scaffold pole, etc. (4) to decorate the scaffold - used for decoration engineering construction work. (5) structure of the scaffold - used for building and structure engineering construction work. (6). Cantilever scaffold - applied to equipment installation or maintenance cantilevers. http://www.hunanworld.com/

Housing construction project: frame scaffolding materials preparation

图片
Housing construction project: frame scaffolding materials preparation (1) the door frame, bear the load from the upper. 2 crossbar: limit the door frame lateral displacement, increase the stiffness, shear supporting role. (3) expand the pressure surface, adjusting the scaffold of horizontal and vertical degree. (4) locking arm: restrictions on the vertical displacement, next door frame. (5) barge core: upper and lower door frame the positioning of the link rod. (6)the pedals: can enhance the whole stiffness of the scaffold. (7)Once connecting rod: and the structure of attachment, maintain the stability of the scaffold. (9)Being horizontal reinforcing rod: strengthen the overall stiffness of scaffold. levies crossed reinforcing rod: strengthen the overall stiffness of scaffold. ⑽ fasteners: rotation and right-angle fastener fasteners. ⑾ boarding ladder: use on the scaffold. ⑿ : parallel to the frame instead of the pedals for overall stiffness enhance the scaffold. http://ww

Housing construction project: cuplock scaffolding forms and components

图片
Housing construction project: cuplock scaffolding forms and components form Cuplock type steel pipe scaffold is developed by China refer to foreign experience a kind of multi-functional scaffolding, its member nodes connected by bowl, because the bowl is fixed on the steel pipe, all axial component connection, good mechanics performance, reliable connection, scaffolding of integral sex is good, there is no buckle loss problem. components Cuplock type steel pipe scaffold made by steel tube pole, cross bar, bowl joint, etc. Its basic construction and erection requirements and fastener type steel pipe scaffold is similar, the difference lies mainly in bowl buckle joint. Bowl buckle joint by joint on button bowl, the bowl, bar and the bowl on the limit pin, etc. On the stud welding under the limit pin buckle bowl and the bowl, the bowl set into the stud. On the rail and diagonal welding plugs. Assembly, the rail and the inclined rod inserted into the bowl, compression and rotation on

Housing construction project: scaffolding working conditions have what characteristic

图片
Housing construction project: scaffolding working conditions have what characteristic 1, by load variation. 2, fasteners, belong to semi-rigid connection nodes and node rigid size is associated with fastener quality, installation quality, node performance there is a big variation. 3, scaffolding structure and component of initial defects, such as initial bending of bar, rust, erection size error is larger, the eccentric load, etc. 4, and the wall connection, bigger binding variation on the scaffold. The above accumulation and statistical data, the study of the problems of the lack of system does not have independent probability analysis condition, so the structural resistance adjusting multiplied by the coefficient of less than 1 its value system with using the safety factor of the calibration. Therefore, the specification adopts the design method of essentially belongs to half probability, half experience. The structure of the scaffold to satisfy the provisions of this specificati

Housing construction project: frame scaffolding to dismantle the point

图片
Housing construction project: frame scaffolding to dismantle the point 1) the preparing work before dismantling scaffolding: comprehensive review scaffolding, focusing on fasteners connecting fixed, such as supporting system meets the safety requirements. According to the test results and field situation and prepare the demolishing scheme and the department for approval. Technical clarificaiton. According to the demolition of the scene of the situation, fences or warning signs, there and watch. Retained in the removal of scaffolding materials, wires and other sundry. 2) the demolition of frame work areas, prohibit the operation personnel to enter. 3) before disassembly, shall have the site construction manager's approval formalities, specialist command is required when open shelves, do echo, up and down movement coordination. 4) after dismantling order should be raised parts, first raised parts before, it is forbidden to use pushed or pulled down the demolition of practice. 5)

Housing construction project: scaffolding, technical requirements

图片
Housing construction project: scaffolding, technical requirements 1, no matter what type of erection of scaffolding, scaffold material and used in the processing quality, must conform to specified requirements is absolutely forbidden to use unqualified erection of scaffold materials, in case of accident. 2, general scaffolding must be scaffolding set-up, security technology operating rules for height more than 15 m or more tall scaffolding, must have the design, calculation and detailed, the erection scheme, technical director at the next higher level for examination and approval, have a written safety technical clarificaiton, before the erection. 3, risk for large and special crane, pick, hang, socket, stacking shelves must also pass design and the examination and approval. Prepare a separate safety technical measures, to the erection. 4, after the construction team to accept tasks, must organize personnel, carefully grasp the scaffold, special safety construction organization des

Housing construction project: frame scaffolding requirements

图片
Housing construction project: frame scaffolding requirements 1, frame scaffolding foundation must be solid, and should do well in drainage slope, in case of water. 2, frame scaffolding, order: basic preparation to put plate, put the base - vertical two common single door frame and install the crossbar to install scaffolding, on this basis, repeat install door frame and cross bar, scaffold board process. 3, frame steel pipe scaffold should start at one end to the other end of the set-up, shangbu scaffold should be done in the next step after the completion of the scaffold erection. The erection direction contrary to the next step. 4, frame scaffold erection, should first base in the endpoint insert two common door frame, and then fitted with fixed cross rod, lock the lock plate, and then after the erection of the door frame, each cross, cross rod and locks fitted immediately. 5, the scaffold must be set with reliable link building. 6, the outer edge of the frame steel pipe scaffol

The removal of housing construction project: the scaffold construction technology

图片
The removal of housing construction project: the scaffold construction technology Disassembly procedures shall comply with the top-down, to build after the demolition of the principle, general demolition order: safety net - rail - scaffolding to bracing, lateral horizontal pole to longitudinal rod, rod. No discrete surface split or disassemble frame at the same time in the upper and lower two steps. Do it step by step, a rod. Tear open poling, want to embrace poling first, then open the last two buckle. Demolition of longitudinal rod, brace, bracing, should first open the middle buckle, then hold the middle, and end button. All the wall bar and so on must be demolished with scaffolding synchronization, it is strictly prohibited to even the wall again after a whole layer or layers of dismantling scaffolding. Piecewise demolition of elevation difference should not be greater than 2 steps, such as the elevation difference is greater than the step 2, should add the wall reinforcement.

Construction project management: scaffold and its foundation stage for inspection and acceptance

图片
Construction project management: scaffold and its foundation stage for inspection and acceptance 1 before, after the completion of the foundation and scaffolding. 2, homework load before on the layer. 3, after every erection of the 6 m to 8 m height. 4, meet the design height. 5, meet after more than six levels of strong wind and the wind or rain, frozen thawed in the region. 6 and stop using more than one month. http://www.hunanworld.com/

Three major factors influencing price of scaffolding

图片
Three major factors influencing price of scaffolding With the development of construction industry now, scaffolding market expanding, the market is more and more mature. Many large and small scaffold construction equipment manufacturers in the production of these basis, the scaffolding on the market are a diverse group, different function, quality is uneven. In the face of so many varieties, scaffolding the price will be a key factors to become buyers think, sometimes even is a key element, but in contrast the price also can not ignore the quality of your goods. The following introduction of three factors affect the price of scaffolding: First, different mobile scaffolding manufacturer will appear different quotation, quality is not the same, should pay attention to its generality, bearing strength, firmly the basic quality problems, such as this to help construction workers have a direct impact. Second, scaffolding should follow the rules of the market price, in quality a

Hunan World Scaffolding Co., Ltd Attend Carton Fair and Product Popularity

图片
Hunan World Scaffolding Co., Ltd Attend Carton Fair and Product Popularity The 119th Session of Cahton Fair is held on April in Guangzhou. The fair is known as China's "trade barometer" in the world and attracting merchants to participate,negotiate and sign on exhibition from around the world. Hunan World Scaffolding Co., Ltd, as subsidiary of Shinestar Holdings Group Co.,Ltd with excellent product quality in this year's trade, obtain a large number of overseas customers.  All along, the Canton Fair with its international, professional and business characteristics, for many domestic and foreign enterprises, exhibitors and buyers sought after, World through this international platform to fully display their strength, this is more the new portfolio of exhibitors, showing excellent star lineup scale. At this Canton fair, World Scaffolding exhibited many products including Hot galvanized metal planks,scaffolding systems and coupler systems.Such  new prod

Rotating fastener installation accuracy for the engineering quality and safety is very important

图片
http://www.hunanworld.com/ Rotating fastener installation accuracy for the engineering quality and safety is very important Up to now has placed great emphasis on the construction safety, rotating fastener used for scaffolding tube center, is used to establish the connection between the rod and bar, its significance in the process of the construction of the scaffold, therefore, demand for its quality is very high. And precise installation problem is one of the important factors to ensure the stability of the scaffold structure, therefore, we should pay attention to the following points during the installation process. Installation accuracy, determines the fasteners in engineering science, it is strictly prohibited. The matching of the rotating fastener installation accuracy, in order to make the product with the pipe connect to get an accurate result, at the same time, must not make construction fasteners deformation measuring method and measuring tools, and then we to the f

When the scaffolding products is corrupt, we are going to do?

图片
http://www.hunanworld.com/ When the scaffolding products is corrupt, we are going to do? Scaffolding today use scope is extremely broad, they appear in building architecture strike up a conversation or more stage structure, and no matter what a kind of architecture, we must note that deposit is bad to the scaffold, corrupt they will happen, so, when the scaffolding products is corrupt, we are going to do? It is understood that after the corrupted the scaffold will be too fragile, especially metal them, strong performance will be lost, especially after the rusting of the scaffold, there will be a very fragile situation, as long as the impact, it may break. Therefore, if found a scaffolding decay, for immediate measures, for example, to spray paint or rust-proof oil pipe rack etc. Scaffolding of corruption, of course, also can give the lack of performance, in order to unnecessary trouble, when the scaffold is corrupt, we don't use them, the best way is to replace a scaffol

What are the requirements production design coupler scaffoldinging?

图片
http://www.hunanworld.com/ What are the requirements production design  coupler  scaffold inging ? Along with the development of the domestic economy, the market prospect of the scaffold is becoming more and more clear,  coupler  scaffold inging  because of its unique advantages, occupying most of the market and has never been surpassed, and its development space is very big in the future. coupler  scaffold inging  of large bearing capacity, convenient installation, setting up is very flexible, because it is can adjust the length of steel tube, fastener connections between the easy, so it can adapt to all kinds of buildings or facade with scaffolding. Second, its processing is simple, low investment costs, the use of material also can achieve very good effect, so it is a kind of economical set of scaffold. The  coupler  scaffold inging  has so many advantages, the production design from time to tome what requirements? Whichever one type of scaffolding to build-up,  coupl