Housing construction project: scaffolding safety related requirements

Housing construction project: scaffolding safety related requirements
1, the build-up of high-level scaffolding, adopted by the various materials must meet the quality requirements.
2, high-level scaffolding foundation must be strong, before the erection of the computation, meet the requirement of load, and set-up, and according to the construction of drainage measures.
3, scaffolding, technical requirements should comply with the regulations of relevant specification.
4, must attach great importance to all kinds of structural measures: bridging, node, etc. Shall be set up according to the requirement.
5, horizontal closed: should be the first step, every step or two step, be put with scaffolding plank hand or foot basketry, scaffolding to laid along, overlapping joint should be shelved in a small bar, it is forbidden to appear short board. And in every four step laid between stud and metope system bottom has long security.
Step 6, vertical closed: from the second to fifth step, each step all needs to the stud unavoidably side set up in 1.00 m high protective railings and pedal or set up network, protective pole (network) and vertical pole fastened up. Step 5 above in addition to the set a guard rail, set net should be all set its safety or security. In concentration areas or residents along the street, it should be the second step, the outside all set net set its safety or security.
7, scaffolding, should be higher than 1.5 m above the top of the building or operating and added palisade.
8, the erection of scaffolding steel, fasteners, scaffolding and connections shall not be arbitrarily dismantled. Construction when necessary, must be subject to consent by the site, head, and take effective measures to process is completed, immediately recover.
9, scaffolding before use, should by the examination and acceptance of construction site, head of the organization, and present the single fill in the acceptance of rear can use. In construction process should have professional management, inspection and maintenance, and regular settlement observation, found abnormal should take timely reinforcement measures.
10, scaffolding demolition, it shall first check connections and buildings, and the remaining on the scaffold material, debris and other clean, from top to bottom, according to the loading before, after the first open order, demolition of the material should be unified transfer or hanging down to the ground, step by step. Are not allowed to step down the method, it is forbidden to throw down or push (la) and fall for.
11, take down the scaffolding, should set the alert, and hold people alert. In case of more than 6 wind and bad weather, should stop scaffolding demolition work.
12, the requirement of the foundation, the foundation is not usual, please use the controllable pitch base feet, equilibrium. The foundation must be capable of scaffolding and work under pressure.
13, staff building, and high altitude work must wear a seat belt, work area around please install safety net, prevent weight drops, injuring others.
14 the component, accessories, scaffolding is strictly prohibited in the process of transportation, storage serious fall, hit. Lap, tear open outfit, it is strictly prohibited thrown from a height, remove from down operation in sequence.
15, use process pay attention to safety, it is forbidden to play on the shelf, put an end to accidents.
16, work is important, safety, life is more important, please keep in mind the above content.