World scaffolding construction scheme scaffolding demolition method

World scaffolding construction scheme scaffolding demolition method

Scaffold construction scheme
Project summary:
1, the structure of the planar dimension, layer number and height, total height, the building area, structure, geological conditions and time limit for a project; Scaffold outside the scheme selection, etc.
2, compilation basis,
(1) "technical specification for construction fastener type steel pipe scaffold safety JGJ 130-2001 - J 2001-84 (2002)
(2) "construction safety inspection standards" JGJ 59-99
(3) the geological investigation report
(4) the construction drawings
Second, the scaffold design
1, determine the scaffolding steel tube, fastener, scaffolding, and even the wall materials;
2, determine the scaffold structure size, height and foundation treatment scheme shall be built;
Step 3, determine the scaffold from the relative position, poling horizontal distance, bar;
4, determine the erection location of bracing and requirements;
5, to determine the wall connection, distance;
6, to determine the upper and lower construction operation channel set mode and position;
7, block set foot.
Third, design and calculation
1, identify and map scaffolding, construction scheme and design calculation diagram;
Article 2, determine the scaffold design load (4.1, 4.2, 4.3);
Article 3, poling foundation bearing capacity calculation (5.5);
4, longitudinal and transverse horizontal pole of flexural member strength and connection fastener against sliding bearing capacity calculation of (5.2);
5, poling stability and poling section (5.3) for calculating the axial force;
6, even the wall of strength, stability, and the connection strength calculation (5.4);
7, the formwork support rod stability and poling section (5.6) for calculating the axial force.
Fourth, construction organization and management
1, the erection of scaffolding shall have corresponding qualifications of professional construction team construction; Determine the construction unit should be clear head and full-time security officer at the same time.
2, scaffolding, staff must be after according to the current national standard "special operations personnel safety technical appraisal management rules GB5036 examination qualified scaffolder.
3, mount guard personnel should be regular physical examination, eligible may show certificates.
Five, scaffolding construction quality requirement and acceptance
1, construction preparation.
(1) unit leaders to set up and use personnel disclosure;
(2) in steel, fasteners, scaffolding, safety nets and other components for inspection and acceptance;
(3) cleaning, flat ground to ensure that the drainage unblocked.
2, scaffolding foundation and foundation construction, basic acceptance, pay-off.
3, scaffolding, schedule control.
4, the technical requirements of the scaffold erection, allowable deviation and method of examination and acceptance.
5, scaffolding safety practices and requirements.
6, scaffolding demolished.
Scaffolding demolition method
(1) demolition job according to the erection job instead procedures, follow from top to bottom, to build after the demolition, to dismantle the principle of first, after the first rail, scaffolding, bracing, tear open a small bar, bar, after poling, etc., according to the principle of a clear step in turn;
(2) it is strictly prohibited to up and down on at the same time;
(3) open poling, should first hold stud again open the last two buttons. Tear open the ledger, bracing, should first open the middle button, and then hold the middle, and end clasp solution;
Rod (4) the wall in the upper bar after the demolition (except stretch up poling) can be torn down;
(5) loosen the fastening of the flat bar should be removed at any time, must not loose on the shelf;
(6) removed long bar should be two people work together, in order to avoid mistakes when working alone.
(7) remove the bar should be lifting to the ground, may not throw down;
(8) to the ground rod parts should be specified location, increases with the increasing demolition, classification, pattern on the day on the day of the qing dynasty.