The Frame Scaffolding System in the Construction Project

1, the erection of frame scaffolding
2, frame scaffolding, order: basic preparation to put plate, put the base - vertical two common single door frame and install the crossbar to install frame scaffolding, on this basis, repeat install door frame and cross bar, frame scaffolding board process.
3, foundation must be solid, and appropriate pave 100 mm slag layer and the desire and should do well drainage slope, in case of water.
4, door type steel pipe frame scaffolding should begin from the end to the other end, frame scaffolding should be done in the next step after the completion of the frame scaffolding erection. The erection direction contrary to the next step.
5, the first step of frame scaffolding erection, should first base in the endpoint insert two common door frame, and then fitted with fixed cross rod, lock the lock plate, and then after the erection of the door frame, each cross, cross rod and locks fitted immediately.
6, the outer edge of the door type steel pipe frame scaffolding bracing should be set up, the vertical and longitudinal shall be set up in a row.
7, the frame scaffolding must be set with building reliable links, links to a spacing of transverse frame shall not be greater than the step 3, shall not be greater than the vertical step 3 (frame scaffolding height < 20 m), 2 step (frame scaffolding height > 20 m).
8, the removal of frame scaffolding
The preparing work before 9, dismantle frame systems scaffolding: comprehensive review of frame scaffolding, focusing on fastener connection fixed, such as supporting system meets the safety requirements; According to test results and preparation of demolition scheme and the site condition and approved by the department.